How to do preparation works for jaw crusher before commissioning in crushing plant?
Source:www.dieselcrusher.com Author:Great Wall Company Views:
After installation of jaw crusher, we have to do commissioning before being used in aggregate crushing plant and quarry crushing plant. There are some preparation works of jaw crusher to ensure smooth running in crushing plant. How to do preparation works for jaw crusher before commissioning in stone crushing plant ? We can consult with processional mining machinery manufacturer, Great Wall Company conducts some conclusion for you to guarantee jaw crusher reliable performance in trial running in crushing plant.
1, you should carefully check that all fasteners are fully tightened.
2, Make sure the transmission belt is good, when there is oil on the belt or belt pulley, it should be cleaned.
3, you should carefully check the lubrication of the bearings, ensure sufficient lubricant of jaw crusher bearings.
4, Jaw crusher starts must be in a load-free State, please confirm no raw materials between movable jaw plate and fixed jaw plate.
5, when jaw crushers process high hard rocks, maximum feeding particle size should be less than two thirds width of feed opening size.